Motorists can resume using Cherry Hill after large-scale construction project wraps upFinally REady

Cherry Hill from Telegraph to Outer Drive reopened Friday, Dec. 7, after crews concluded a large-scale construction project on one of the City’s main residential corridors.

The federally-funded project included the replacement of sewers, water main and concrete.

The project was administered by the Michigan Department of Transportation and managed by Rowe Consultants.

Construction on Cherry Hill began in May 2018. The project was slated to be completed by October 2018. However, a statewide labor dispute between a heavy equipment operators union and an organization of road construction contractors delayed the project’s completion in September.